PennDOT Performing Rebuild of I-80 Interchange in East Stroudsburg : CEG

2022-05-29 00:29:35 By : Ms. Summer Tao

Mon May 02, 2022 - Northeast Edition Pocono Record & PennDOT

The East Stroudsburg interchange at Interstate 80 is undergoing a major construction rehabilitation, which is to include roadway expansion, new bridges and multiple traffic roundabouts in the northeastern Pennsylvania city — all to stay in step with the community's growth and development.

The $93.9 million "Eastburg Project," as it is known locally, recently broke ground and construction crews are under way at the Exit 308 site, the Pocono Record in Stroudsburg noted on April 26.

The twin communities of East Stroudsburg-Stroudsburg have experienced a tremendous amount of growth in the past decade, the newspaper said, and continues to see more expansion with nearby residential and commercial developments. According to the Pennsylvania Department of Transportation (PennDOT), this has pushed the traffic volumes beyond the capacity intended of the current infrastructure.

This section of the I-80 corridor sees an average of nearly 80,000 vehicles daily, of which 22 percent are trucks, revealed PennDOT. Exit 308 also is known as the Prospect Street exit and brings in daily traffic to Lehigh Valley Hospital — Pocono, East Stroudsburg University, downtown East Stroudsburg's Crystal Street and the shopping plazas along Lincoln Avenue that include Walmart and the Giant Food Market.

The rebuilding effort was originally slated to start in 2020, prior to the COVID-19 pandemic.

PennDOT has begun installing barriers along I-80 at the Prospect Street exit, signaling the start of a four-year construction project that will last through July 2026.

According to a project report found on the PennDOT website, the general contractor for the interchange rebuild is J.D. Eckman Inc., based in Atglen, Pa.

"The project is going to replace the Prospect Street bridge over I-80 and also the bridge that carries over Lincoln Avenue," said Ron Young, an officer of PennDOT. "It will extend ramps on and off I-80 and will bring new roundabouts on both sides of I-80 at this intersection. These roundabouts will be like the one at the Delaware Water Gap Exit 310."

The reconfiguration of the Exit 308 interchange also will bring a fresh look and feel as the two roundabouts will lead to the creation of several local street realignments, Young explained, as well as add a signal at the new T-intersection of Prospect Street and Forge Road/Greentree Drive and bring signal improvements to the Prospect Street and East Brown Street intersection.

In rebuilding the freeway exit, I-80 is to be widened from its current four lanes to six lanes in east Stroudsburg, and the Prospect Street Bridge will be replaced. That overpass is being designed to meet the current vertical clearance standards over I-80, making it taller and wider.

A little further west, the project also will rebuild the mainline bridge over Lincoln Avenue and the former DL&W Railroad.

PennDOT noted the reconstruction of the interchange ramps will make them longer than the existing ramps to allow traffic to better get up to speed and to slow down. The rebuild also will create several retaining walls along I-80 to limit the impact on the right-of-way.

PennDOT outlined the focal points of the five stages of the Eastburg Project just before the work began:

East Stroudsburg Borough Manager Brian Bond lauded the I-80 Exit 308 Interchange project when he told the Pocono Record that when completed in 2026, "It will feel more like a gateway, welcoming people entering East Stroudsburg Borough from Interstate 80. Prospect Street will be widened from East Brown to Center Street and lined with sidewalks and decorative lighting."

The Exit 308 reconfiguration was described by PennDOT as the next step in a long-range plan to widen and improve the interstate from the Delaware River at the point where the highway enters the state from New Jersey. Part of the effort includes raising bridges to accommodate tractor trailers passing underneath them.

The Pocono Record noted that three bridges on I-80 have already been built in Pennsylvania from the Delaware Water Gap Plaza, along with new ramps, roundabouts and some expansion of the interstate.

PennDOT's overall I-80 Reconstruction Project includes another 3.5 mi. of interstate roadway reconstruction, encompassing Exit 307 to a point just west of Exit 303, all with similar interchange plans and a new flyover lane taking westbound traffic to U.S. Highway 209 and a newly constructed full interchange off I-80 accessing both directions of PA Route 611 at the Shoppes at Stroud Plaza. Changes to the existing Main Street and Dreher Avenue exists also are planned.

Young said the next portion of the I-80 Reconstruction effort is in the final design stage.

"If all moves according to plan, [the design] should be done by end of this year and then out for bid," he explained. "[The rebuild] could possibly break ground sometime next year."

WisDOT Improves Safety With $136M Bypass

Kelly Tractor Hosts Cat Operator Challenge at Miami Headquarters

Cullman Regional Hospital Undergoing $30M Expansion

Bobcat Brings Electric-Powered Construction Equipment Innovations to California

Doosan Announces Its Top-Performing North American Dealers of 2021

Hyundai Construction Equipment Americas Names Shafer Equipment Dealer of West Virginia

Hills Machinery Holds Grand Opening for New Leland, N.C., Facility

Decade After Bridge Was Demolished, Maine Town Hopes for New One Soon

Construction Equipment Guide 470 Maryland Drive Fort Washington, PA 19034 800-523-2200

Construction Equipment Guide covers the nation with its four regional newspapers, offering construction and industry news and information along with new and used construction equipment for sale from dealers in your area. Now we extend those services and information to the internet. Making it as easy as possible to find the news and equipment that you need and want.

Contents Copyrighted 2022, by Construction Equipment Guide, which is a Registered Trademark, registered in the U.S. Patent Office. Registration number 0957323. All rights reserved, nothing may be reprinted or reproduced (including framing) in whole or part without written permission from the publisher. All editorial material, photographs, drawings, letters, and other material will be treated as unconditionally assigned for publication and copyright purposes and are subject to Construction Equipment Guide’s unrestricted right to edit and comment editorially. Contributor articles do not necessarily reflect the policy or opinions of this publication. Read our privacy policy here.